A- A A+ English Hindi
Loading...
Report ME4- Project wise Current Status of Capacity Building Activities, UGs, SHGs, FPOs, EPAs, Production System and Livelihood Activities
Report ME4- Project wise Current Status of Capacity Building Activities, UGs, SHGs, FPOs, EPAs, Production System and Livelihood Activities for District 'LEH LADAKH' of State 'UT of LADAKH'

Report as on: 23/11/2024 06:10 PM

S.No. Project Name No. of User Groups Reported No. of SHGs Reported No. of FPOs No. of EPAs Reported No. of Production System Activities Reported No. of Livelihood Activities for the Asset-less Persons Reported
1 2 3 4 5 6 7 8
1 LEH LADAKH-WDC - 1 /2022-23 0 0 0 7 0 0
2 LEH LADAKH-WDC - 2 /2022-23 0 0 0 4 0 0
3 LEH LADAKH-WDC - 3 /2022-23 0 0 0 7 0 0
4 LEH LADAKH-WDC - 4 /2022-23 0 5 0 5 2 3
5 LEH LADAKH-WDC - 5 /2022-23 0 0 0 6 4 0
6 LEH LADAKH-WDC - 6 /2022-23 0 0 0 7 0 0
Grand Total 0 5 0 36 6 3