A- A A+ English Hindi
Loading...
Report ME2- Project-wise Current Status of Project Plans Created, No. of WCDC and PIA Accounts and No. of Projects with Baseline Ground Water Details
Report ME2- Project-wise Current Status of Project Plans Created, No. of WCDC and PIA Accounts and No. of Projects with Baseline Ground Water Details for District 'ANJAW' of State 'ARUNACHAL PRADESH'

Report as on: 21/11/2024 10:17 PM

S.No. Project Name Total no. of Village Covered in Project No. of Project for Permission given No. of Project Plan Created No. of Project with Baseline Ground Water
1 2 3 4 5 6
1 ANJAW-WDC - 1 /2021-22 14 1 1 1
Grand Total 14 1 1 1