Report as on: 21/11/2024 10:46 PM
S.No. | Project Name | Total no. of Village Covered in Project | No. of Project for Permission given | No. of Project Plan Created | No. of Project with Baseline Ground Water |
---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 |
1 | SAGAR-WDC - 1 /2021-22 | 20 | 1 | 1 | 1 |
2 | SAGAR-WDC - 2 /2021-22 | 30 | 1 | 1 | 1 |
3 | SAGAR-WDC - 3 /2022-23 | 17 | 1 | 1 | 1 |
4 | SAGAR-WDC - 4 /2022-23 | 15 | 1 | 1 | 1 |
Grand Total | 82 | 4 | 4 | 4 |