Report ME2- Project-wise Current Status of Project Plans Created, No. of WCDC and PIA Accounts and No. of Projects with Baseline Ground Water Details
Report ME2- Project-wise Current Status of Project Plans Created, No. of WCDC and PIA Accounts and No. of Projects with Baseline Ground Water Details for District 'PAPUM PARE' of State 'ARUNACHAL PRADESH'

Report as on: 24/11/2024 04:43 AM

S.No. Project Name Total no. of Village Covered in Project No. of Project for Permission given No. of Project Plan Created No. of Project with Baseline Ground Water
1 2 3 4 5 6
1 PAPUM PARE-WDC - 1 /2021-22 12 1 1 1
2 PAPUM PARE-WDC - 2 /2021-22 8 1 1 1
3 PAPUM PARE-WDC - 3 /2021-22 10 1 1 1
4 PAPUM PARE-WDC - 4 /2021-22 2 1 1 1
Grand Total 32 4 4 4