A- A A+ English Hindi
                       
Loading...
Report PE3 - Project-wise Mid Term Project Evaluation of Cropped Area Details
Report PE3 - Project-wise Mid Term Project Evaluation of Cropped Area Details for District 'SOUTH GARO HILLS' of State 'MEGHALAYA'

Report as on: 10/11/2026 10:16 PM

State Name : MEGHALAYA
S.No. Project Name Gross Cropped Area (ha.) Total Gross Cropped Area (ha.) Area under Plantation Cover (ha.) Area of Culturable Wasteland (ha.)
Kharif Crop Rabi Crop Third Crop Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area
Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area Pre Project Status (Aggregate) Mid Project Status (Aggregate) Controlled Area
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1 SOUTH GARO HILLS-WDC - 1 /2021-22 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 SOUTH GARO HILLS-WDC - 2 /2021-22 235.0000 340.00 294.0700 10.0000 16 0.0000 0.0000 0.00 0.0000 245.0000 356.00 294.0700 390.0000 400.9100 27.9200 0.0000 5.0000 0.0000
3 SOUTH GARO HILLS-WDC - 3 /2022-23 70.0000 71.5 13.0000 0.0000 0.00 0.0000 246.0000 248 43.0000 316.0000 319.50 56.0000 5.0000 5.0000 2.0000 6.0000 5.5000 2.0000
Grand Total 305.0000 411.50 307.0700 10.0000 16.00 0.0000 246.0000 248.00 43.0000 561.0000 675.50 350.0700 395.0000 405.9100 29.9200 6.0000 10.5000 2.0000
×