Report as on: 05/06/2026 02:18 AM
| S.No. | Project Name | Water Harvesting Structures Constructed/Revived(in No.) | ||||
|---|---|---|---|---|---|---|
| 2022-23 | 2023-24 | 2024-25 | 2025-26 | 2026-27 | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1 | SINDHUDURG-WDC - 1 /2021-22 | 0 | 0 | 0 | 38 | 0 |
| 2 | SINDHUDURG-WDC - 2 /2021-22 | 0 | 0 | 17 | 22 | 0 |
| 3 | SINDHUDURG-WDC - 3 /2021-22 | 0 | 0 | 0 | 20 | 0 |
| 4 | SINDHUDURG-WDC - 4 /2021-22 | 0 | 0 | 25 | 30 | 13 |
| 5 | SINDHUDURG-WDC - 5 /2021-22 | 0 | 0 | 23 | 32 | 1 |
| 6 | SINDHUDURG-WDC - 6 /2021-22 | 0 | 0 | 11 | 22 | 1 |
| 7 | SINDHUDURG-WDC - 7 /2021-22 | 0 | 0 | 6 | 13 | 20 |
| 8 | SINDHUDURG-WDC - 8 /2021-22 | 0 | 9 | 4 | 15 | 2 |
| 9 | SINDHUDURG-WDC - 9 /2021-22 | 0 | 0 | 5 | 25 | 0 |
| Grand Total | 0 | 9 | 91 | 217 | 37 | |