S.No. Project Name Financial Year(2022-23) Financial Year(2023-24) Financial Year(2024-25)
No. of Project Plan Created No. of Project Achievement Created No. of Project Plan Created No. of Project Achievement Created No. of Project Plan Created No. of Project Achievement Created
1 2 3 4 5 6 7 8
1 PALGHAR-WDC - 1 /2021-22 0 0 1 0 1 1
2 PALGHAR-WDC - 2 /2021-22 0 0 1 0 1 1
3 PALGHAR-WDC - 3 /2021-22 0 0 1 0 1 1
4 PALGHAR-WDC - 4 /2021-22 0 0 1 0 1 0
5 PALGHAR-WDC - 5 /2021-22 1 0 1 0 1 1
6 PALGHAR-WDC - 6 /2021-22 0 0 1 0 1 1
7 PALGHAR-WDC - 7 /2021-22 1 0 1 0 1 1
8 PALGHAR-WDC - 8 /2021-22 0 0 1 0 1 1
Grand Total 2 0 8 0 8 7