Report as on: 24/03/2026 03:51 PM
| S.No. | Project Name | NRM Works | EPA Works | Livelihood Works | Production Works | Total Work Code excluding Foreclosed (NRM(4+5+6) + EPA(8+9+10) + LIV(12+13+14) + PROD(16+17+18)) | Total Geotag Work Code | Total Non Geotag Work Code (19-20) | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | |||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 |
| 1 | CHITTOOR-WDC - 1 /2021-22 | 206 | 0 | 1 | 180 | 37 | 0 | 0 | 33 | 0 | 0 | 0 | 0 | 313 | 0 | 3 | 310 | 527 | 407 | 120 |
| 2 | CHITTOOR-WDC - 2 /2021-22 | 247 | 0 | 2 | 211 | 46 | 0 | 0 | 36 | 0 | 0 | 0 | 0 | 206 | 0 | 1 | 205 | 455 | 300 | 155 |
| 3 | CHITTOOR-WDC - 3 /2021-22 | 261 | 0 | 1 | 224 | 40 | 0 | 0 | 17 | 0 | 0 | 0 | 0 | 247 | 0 | 0 | 247 | 489 | 295 | 194 |
| 4 | CHITTOOR-WDC - 4 /2021-22 | 435 | 0 | 1 | 362 | 52 | 0 | 0 | 52 | 0 | 0 | 0 | 0 | 339 | 0 | 7 | 332 | 754 | 501 | 253 |
| 5 | CHITTOOR-WDC - 5 /2021-22 | 253 | 0 | 1 | 218 | 19 | 0 | 0 | 19 | 0 | 0 | 0 | 0 | 427 | 0 | 17 | 410 | 665 | 421 | 244 |
| 6 | CHITTOOR-WDC - 6 /2021-22 | 221 | 0 | 4 | 168 | 44 | 0 | 3 | 30 | 0 | 0 | 0 | 0 | 735 | 0 | 0 | 735 | 940 | 588 | 352 |
| 7 | CHITTOOR-WDC - 7 /2021-22 | 207 | 0 | 13 | 165 | 58 | 0 | 0 | 50 | 0 | 0 | 0 | 0 | 306 | 0 | 5 | 301 | 534 | 399 | 135 |
| Grand Total | 1830 | 0 | 23 | 1528 | 296 | 0 | 3 | 237 | 0 | 0 | 0 | 0 | 2573 | 0 | 33 | 2540 | 4364 | 2911 | 1453 | |