S.No. Project Name NRM Works EPA Works Livelihood Works Production Works Total Work Code excluding Foreclosed (NRM(4+5+6) + EPA(8+9+10) + LIV(12+13+14) + PROD(16+17+18)) Total Geotag Work Code Total Non Geotag Work Code (19-20)
Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 SOUTH GARO HILLS-WDC - 1 /2021-22 135 17 0 118 0 0 0 0 0 0 0 0 0 0 0 0 135 27 108
2 SOUTH GARO HILLS-WDC - 2 /2021-22 267 26 0 241 0 0 0 0 0 0 0 0 0 0 0 0 267 60 207
3 SOUTH GARO HILLS-WDC - 3 /2022-23 67 42 0 25 0 0 0 0 0 0 0 0 0 0 0 0 67 5 62
Grand Total 469 85 0 384 0 0 0 0 0 0 0 0 0 0 0 0 469 92 377