A- A A+ English Hindi
                       
Loading...
Report GT2- Work Code Status with Geotagging Details
Report GT2 - Project Wise Work Code Status with Geotagging Details for District "JALORE" of State "RAJASTHAN"

Report as on: 04/08/2026 08:16 PM

S.No. Project Name NRM Works EPA Works Livelihood Works Production Works Total Work Code excluding Foreclosed (NRM(4+5+6) + EPA(8+9+10) + LIV(12+13+14) + PROD(16+17+18)) Total Geotag Work Code Total Non Geotag Work Code (19-20)
Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed Total Works Not Started (Status Not Submitted) Ongoing Completed
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
1 JALORE-WDC - 1 /2021-22 1101 219 0 859 12 0 0 12 0 0 0 0 0 0 0 0 1090 413 677
2 JALORE-WDC - 2 /2021-22 423 3 1 415 12 0 0 12 0 0 0 0 0 0 0 0 431 292 139
3 JALORE-WDC - 3 /2021-22 1112 199 29 884 10 1 0 9 0 0 0 0 0 0 0 0 1122 518 604
4 JALORE-WDC - 4 /2025-26 174 89 1 84 0 0 0 0 0 0 0 0 0 0 0 0 174 46 128
Grand Total 2810 510 31 2242 34 1 0 33 0 0 0 0 0 0 0 0 2817 1269 1548