Report PE7- Project-wise Mid Term Evaluation of Mandays Details


Report as on: 10/11/2026 10:14 PM

S.No. Project Name Farmer`s Average Household Income per Annum (Rs. in Lakhs) No. of Farmers Benefited No. of Persondays Generated (man-days)
Pre - Project Status(Aggregate) Mid - Project Status(Aggregate) Controlled Area Project Area Controlled Area Project Area Controlled Area
1 2 3 4 5 6 7 8 9
1 HOSHANGABAD-WDC - 1 /2021-22 0.4900 0.8100 0.5000 72 N/A 554 N/A
2 HOSHANGABAD-WDC - 2 /2021-22 0.5000 0.8200 0.5000 61 N/A 384 N/A
Grand Total 0.9900 1.6300 1.0000 133 N/A 938 N/A
×