Report as on: 10/11/2026 10:13 PM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | UMARIA-WDC - 1 /2021-22 | 4132.0000 | 5.4542 | 3.6361 | 9.0903 | 4.6839 | 3.1226 | 7.8065 | 4.5002 |
| 2 | UMARIA-WDC - 2 /2021-22 | 4317.0000 | 5.7984 | 3.8989 | 9.6973 | 4.8319 | 3.2213 | 8.0532 | 5.3790 |
| Grand Total | 8449.0000 | 11.2526 | 7.5350 | 18.7876 | 9.5158 | 6.3439 | 15.8597 | 9.8792 | |