Report as on: 10/11/2026 10:14 PM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | SHIVPURI-WDC - 1 /2021-22 | 8000.0000 | 10.5600 | 7.0400 | 17.6000 | 8.6668 | 5.7779 | 14.4447 | 6.6853 |
| 2 | SHIVPURI-WDC - 2 /2021-22 | 6755.0000 | 8.9166 | 5.9444 | 14.8610 | 6.1316 | 4.0877 | 10.2193 | 6.0080 |
| Grand Total | 14755.0000 | 19.4766 | 12.9844 | 32.4610 | 14.7984 | 9.8656 | 24.6640 | 12.6933 | |