Report as on: 10/11/2026 10:13 PM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | RAJGARH-WDC - 1 /2021-22 | 6223.0000 | 8.2143 | 5.4762 | 13.6905 | 5.9052 | 3.9368 | 9.8420 | 3.2206 |
| 2 | RAJGARH-WDC - 2 /2021-22 | 5203.0000 | 6.8679 | 4.5886 | 11.4565 | 5.2708 | 3.5139 | 8.7847 | 4.3197 |
| Grand Total | 11426.0000 | 15.0822 | 10.0648 | 25.1470 | 11.1760 | 7.4507 | 18.6267 | 7.5403 | |