Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 10/11/2026 10:13 PM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 NEEMUCH-WDC - 1 /2021-22 5364.0000 7.0804 4.7203 11.8007 5.3217 3.5478 8.8695 1.2468
2 NEEMUCH-WDC - 2 /2021-22 5275.0000 6.9630 4.6420 11.6050 4.7135 3.1423 7.8558 0.5111
3 NEEMUCH-WDC - 3 /2021-22 5704.0000 7.5292 5.0295 12.5587 4.8773 3.2515 8.1288 0.4338
Grand Total 16343.0000 21.5726 14.3918 35.9644 14.9125 9.9416 24.8541 2.1917
×