Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 10/11/2026 10:13 PM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 KHARGONE-WDC - 1 /2021-22 6114.0000 8.0704 5.3803 13.4507 7.3407 4.8938 12.2345 2.7085
2 KHARGONE-WDC - 2 /2021-22 6975.0000 9.2100 6.1480 15.3580 7.6673 5.1116 12.7789 5.8697
Grand Total 13089.0000 17.2804 11.5283 28.8087 15.0080 10.0054 25.0134 8.5782
×