Report as on: 10/11/2026 10:12 PM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | JHABUA-WDC - 1 /2021-22 | 5027.0000 | 6.6400 | 4.4237 | 11.0637 | 5.5697 | 3.7131 | 9.2828 | 9.7011 |
| 2 | JHABUA-WDC - 2 /2021-22 | 7437.0000 | 9.8268 | 6.5445 | 16.3713 | 7.8813 | 5.2542 | 13.1355 | 9.3221 |
| Grand Total | 12464.0000 | 16.4668 | 10.9682 | 27.4350 | 13.4510 | 8.9673 | 22.4183 | 19.0232 | |