Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 10/11/2026 10:13 PM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 DEWAS-WDC - 1 /2021-22 5710.0000 7.5400 5.0248 12.5648 6.2306 4.1537 10.3843 2.2847
2 DEWAS-WDC - 2 /2021-22 6000.0000 7.9200 5.2800 13.2000 6.6985 4.4657 11.1642 6.2361
Grand Total 11710.0000 15.4600 10.3048 25.7648 12.9291 8.6194 21.5485 8.5208
×