A- A A+ English Hindi
                       
Loading...
Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 10/11/2026 10:12 PM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 ASHOKNAGAR-WDC - 1 /2021-22 6000.0000 7.9200 5.2800 13.2000 4.8648 3.2432 8.1080 6.5934
2 ASHOKNAGAR-WDC - 2 /2021-22 5536.0000 7.3100 4.8716 12.1816 5.3767 3.5845 8.9612 0.3434
Grand Total 11536.0000 15.2300 10.1516 25.3816 10.2415 6.8277 17.0692 6.9368
×