Report as on: 10/11/2026 10:12 PM
| S.No. | Project Name | Sanctioned Project Area (in ha.) | Sanctioned Cost | Fund Utilization | |||||
|---|---|---|---|---|---|---|---|---|---|
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | Fund Received | Total Expenditure (Rs. Crores) | |||||
| Central Share (Rs. Crores) | State Share (Rs. Crores) | Total Share (Rs. Crores) | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
| 1 | ASHOKNAGAR-WDC - 1 /2021-22 | 6000.0000 | 7.9200 | 5.2800 | 13.2000 | 4.8648 | 3.2432 | 8.1080 | 6.5934 |
| 2 | ASHOKNAGAR-WDC - 2 /2021-22 | 5536.0000 | 7.3100 | 4.8716 | 12.1816 | 5.3767 | 3.5845 | 8.9612 | 0.3434 |
| Grand Total | 11536.0000 | 15.2300 | 10.1516 | 25.3816 | 10.2415 | 6.8277 | 17.0692 | 6.9368 | |