A- A A+ English Hindi
                       
Loading...
Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 10/11/2026 10:13 PM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 ANUPPUR-WDC - 1 /2021-22 7212.0000 9.5200 6.3500 15.8700 6.2088 4.1392 10.3480 4.1155
2 ANUPPUR-WDC - 2 /2021-22 5468.0000 7.2200 4.8100 12.0300 4.6863 3.1242 7.8105 9.6442
3 ANUPPUR-WDC - 3 /2021-22 7605.0000 10.0486 6.6924 16.7410 6.3538 4.2359 10.5897 3.3956
Grand Total 20285.0000 26.7886 17.8524 44.6410 17.2489 11.4993 28.7482 17.1553
×