Report PE2- Project-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 10/11/2026 10:13 PM

S.No. Project Name Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10
1 DEOGARH-WDC - 1 /2021-22 5050.0000 8.4840 5.6560 14.1400 8.4840 5.6560 14.1400 1.0100
2 DEOGARH-WDC - 2 /2021-22 5200.0000 8.7360 5.8240 14.5600 8.7360 5.8240 14.5600 1.0100
Grand Total 10250.0000 17.2200 11.4800 28.7000 17.2200 11.4800 28.7000 2.0200
×