Report as on: 24/11/2024 09:48 AM
S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
1 | ANANTAPUR-WDC - 1 /2021-22 | 147 | 46 | 2 | 99 | 0 | 260 | 260 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 341 | 341 | 0 | 0 | 0 | 748 | 647 | 2 | 99 | 0 |
2 | ANANTAPUR-WDC - 2 /2021-22 | 93 | 17 | 0 | 76 | 0 | 47 | 47 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 792 | 792 | 0 | 0 | 0 | 932 | 856 | 0 | 76 | 0 |
3 | ANANTAPUR-WDC - 3 /2021-22 | 132 | 47 | 0 | 85 | 0 | 76 | 76 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 400 | 400 | 0 | 0 | 0 | 608 | 523 | 0 | 85 | 0 |
4 | ANANTAPUR-WDC - 4 /2021-22 | 94 | 26 | 2 | 66 | 0 | 40 | 40 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 366 | 366 | 0 | 0 | 0 | 500 | 432 | 2 | 66 | 0 |
5 | ANANTAPUR-WDC - 5 /2021-22 | 130 | 42 | 1 | 87 | 0 | 21 | 21 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 168 | 168 | 0 | 0 | 0 | 319 | 231 | 1 | 87 | 0 |
6 | ANANTAPUR-WDC - 6 /2021-22 | 127 | 32 | 1 | 94 | 0 | 29 | 29 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 150 | 150 | 0 | 0 | 0 | 306 | 211 | 1 | 94 | 0 |
7 | ANANTAPUR-WDC - 7 /2021-22 | 65 | 19 | 0 | 46 | 0 | 13 | 13 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 432 | 432 | 0 | 0 | 0 | 510 | 464 | 0 | 46 | 0 |
Total | 788 | 229 | 6 | 553 | 0 | 486 | 486 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 2649 | 2649 | 0 | 0 | 0 | 3923 | 3364 | 6 | 553 | 0 |