Report as on: 20/05/2025 10:00 AM
S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
1 | HINGOLI-WDC - 1 /2021-22 | 58 | 11 | 34 | 6 | 7 | 19 | 0 | 0 | 19 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 77 | 11 | 34 | 25 | 7 |
2 | HINGOLI-WDC - 2 /2021-22 | 35 | 2 | 29 | 4 | 0 | 13 | 2 | 0 | 11 | 0 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 49 | 4 | 30 | 15 | 0 |
3 | HINGOLI-WDC - 3 /2021-22 | 114 | 4 | 4 | 98 | 8 | 13 | 1 | 0 | 12 | 0 | 1 | 0 | 1 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 128 | 5 | 5 | 110 | 8 |
Total | 207 | 17 | 67 | 108 | 15 | 45 | 3 | 0 | 42 | 0 | 2 | 0 | 2 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 254 | 20 | 69 | 150 | 15 |