Report as on: 04/12/2024 02:08 PM
S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
1 | GWALIOR-WDC - 1 /2021-22 | 58 | 36 | 0 | 22 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 151 | 151 | 0 | 0 | 0 | 209 | 187 | 0 | 22 | 0 |
2 | GWALIOR-WDC - 2 /2021-22 | 51 | 14 | 0 | 37 | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 40 | 0 | 0 | 0 | 26 | 26 | 0 | 0 | 0 | 117 | 80 | 0 | 37 | 0 |
Total | 109 | 50 | 0 | 59 | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 40 | 0 | 0 | 0 | 177 | 177 | 0 | 0 | 0 | 326 | 267 | 0 | 59 | 0 |