Report as on: 20/04/2025 12:30 AM
S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
1 | GAJAPATI-WDC - 1 /2021-22 | 150 | 4 | 0 | 146 | 0 | 78 | 0 | 0 | 61 | 17 | 111 | 20 | 0 | 64 | 27 | 566 | 0 | 0 | 103 | 463 | 905 | 24 | 0 | 374 | 507 |
2 | GAJAPATI-WDC - 2 /2021-22 | 242 | 0 | 0 | 188 | 54 | 113 | 0 | 0 | 113 | 0 | 67 | 30 | 0 | 37 | 0 | 173 | 0 | 0 | 121 | 52 | 595 | 30 | 0 | 459 | 106 |
Total | 392 | 4 | 0 | 334 | 54 | 191 | 0 | 0 | 174 | 17 | 178 | 50 | 0 | 101 | 27 | 739 | 0 | 0 | 224 | 515 | 1500 | 54 | 0 | 833 | 613 |