Report as on: 04/12/2024 01:51 PM
S.No. | Project Name | Total NRM Works | Total EPA Works | Total Livelihood Works | Total Production Works | Grand Total (NRM+EPA+LIV+PROD) | ||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | Total Works | Not Started (Status Not Submitted) | Ongoing | Completed | Foreclosed | ||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 |
1 | UNA-WDC - 1 /2021-22 | 25 | 8 | 0 | 14 | 3 | 5 | 0 | 0 | 5 | 0 | 4 | 4 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 34 | 12 | 0 | 19 | 3 |
2 | UNA-WDC - 2 /2021-22 | 26 | 5 | 0 | 20 | 1 | 6 | 0 | 0 | 6 | 0 | 8 | 8 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 13 | 0 | 26 | 1 |
3 | UNA-WDC - 3 /2021-22 | 17 | 3 | 3 | 10 | 1 | 5 | 0 | 0 | 5 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 22 | 3 | 3 | 15 | 1 |
Total | 68 | 16 | 3 | 44 | 5 | 16 | 0 | 0 | 16 | 0 | 12 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 96 | 28 | 3 | 60 | 5 |