Report PE2- District-wise Mid Term Evaluation of Sanctioned Cost and Fund Utilization


Report as on: 12/08/2026 06:30 PM

S.No. District Name Total No. of Project Sanctioned Project Area (in ha.) Sanctioned Cost Fund Utilization
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores) Fund Received Total Expenditure (Rs. Crores)
Central Share (Rs. Crores) State Share (Rs. Crores) Total Share (Rs. Crores)
1 2 3 4 5 6 7 8 9 10 11
1 EASTERN WEST KHASI HILLS 2 1250.0000 3.1500 0.3500 3.5000 1.7194 0.1906 1.9100 0.0000
2 EAST GARO HILLS 3 5000.0000 12.6000 1.4000 14.0000 7.9181 0.8797 8.7978 0.3190
3 EAST JAINTIA HILLS 2 1500.0000 3.7800 0.4200 4.2000 2.5869 0.2072 2.7941 0.0919
4 EAST KHASI HILLS 3 1680.0000 4.2336 0.4704 4.7040 2.6507 0.2945 2.9453 1.9216
5 NORTH GARO HILLS 3 1600.0000 4.0320 0.4480 4.4800 2.3820 0.2646 2.6466 0.0000
6 RI BHOI 2 3000.0000 7.5600 0.8400 8.4000 4.4990 0.4999 4.9989 0.0000
7 SOUTH GARO HILLS 3 2000.0000 5.0400 0.5600 5.6000 0.7179 0.0797 0.7976 0.0000
8 SOUTH WEST GARO HILLS 3 3600.0000 9.0720 1.0080 10.0800 5.4132 0.5152 5.9284 0.0327
9 SOUTH WEST KHASI HILLS 3 6800.0000 17.1360 1.9040 19.0400 10.3712 1.1522 11.5235 0.8125
10 WEST GARO HILLS 3 7000.0000 17.6400 1.9600 19.6000 10.0719 1.1189 11.1909 0.0000
11 WEST JAINTIA HILLS 3 5000.0000 12.6000 1.4000 14.0000 8.6268 0.9585 9.5853 0.6879
12 WEST KHASI HILLS 2 2500.0000 6.3000 0.7000 7.0000 4.5854 0.4537 5.0391 0.1107
Grand Total 32 40930.0000 103.1436 11.4604 114.6040 61.5425 6.6147 68.1575 3.9763