Report as on: 29/09/2024 07:59 PM
S.No. | Project Name | Total no. of Village Covered in Project | No. of Project for Permission given | No. of Project Plan Created | No. of Project with Baseline Ground Water |
---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 |
1 | ALMORA-WDC - 1 /2021-22 | 41 | 1 | 0 | 0 |
2 | ALMORA-WDC - 2 /2021-22 | 92 | 1 | 0 | 0 |
3 | ALMORA-WDC - 3 /2021-22 | 52 | 1 | 0 | 0 |
4 | ALMORA-WDC - 4 /2021-22 | 60 | 1 | 0 | 0 |
5 | ALMORA-WDC - 5 /2021-22 | 10 | 1 | 0 | 1 |
6 | ALMORA-WDC - 6 /2021-22 | 5 | 1 | 1 | 0 |
7 | ALMORA-WDC - 8 /2022-23 | 3 | 1 | 0 | 0 |
Grand Total | 263 | 7 | 1 | 1 |