Report ME1- District wise Current Status of Project Location Details Including Total No. of Villages, Total No. of Watershed Committees Constituted, Mapping of Watershed Committees with Villages and No. of Villages Covered under Baseline Survey

Report as on: 29/09/2024 05:52 PM

S.No. District Name Total Projects Sanctioned Project Location Total Village covered in Baseline Survey
No. of Project with Location Details No. of Village Covered in Project Total no. of Watershed Committee No. of Villages Mapped with Watershed Committee
1 2 3 4 5 6 7 8
1 BANKURA 17 12 348 40 261 46
2 BIRBHUM 2 1 51 2 13 3
3 Jhargram 4 1 39 7 39 0
4 MEDINIPUR WEST 2 1 17 3 17 0
5 PASCHIM BARDHAMAN 2 2 63 8 63 0
6 PURULIA 11 2 102 15 65 1
Grand Total 38 19 620 75 458 50