Report CW3- State-wise, District-wise and Project-wise Convergence Work with Expenditure Details
Report CW3- State-wise, District-wise and Project-wise Convergence Work with Expenditure Details

State * District * Project *

Report as on: 29/09/2024 03:56 PM

State : All States   District : All Districts   Project : All Projects
S.No. Head Name Total Works Convergence Works Expenditure Under WDC-PMKSY 2.0 (in Rs.) Expenditure Under Converged Scheme(in Rs.)
1 2 3 4 5 6
1 Area brought under Afforestation / Agriculture / Pasture etc. 112 19 0 0
2 Area brought under Horticulture 117 15 0 0
3 Area covered under Soil and Moisture conservation activities 108 12 0 0
4 Water Harvesting Structure (New created) 198 39 0 0
5 Water Harvesting Structure (Renovated) 72 17 0 0
6 Vegetative and Engineering Structure 80 13 0 0
7 Springsheds 31 10 0 0
Grand Total 718 125 0 0